Book a Visit
Type to search articles or products
Final Cost Breakdown: Every Line Item to Dried Caulk
Home / Journal

Final Cost Breakdown: Every Line Item to Dried Caulk

The Sheet Is Closed

The public Google Sheet that started as a blank file at 10:47 p.m. on a Tuesday now has a final line:

Project Total: $41,400

This post is the full accounting. No rounded summaries. No “approximately.” Every major category, the key line items inside it, and the variance against the original $38,000 estimate. If you have been following the series, you already know the two biggest surprises. Here they sit in context with everything else we actually spent.

Original Estimate vs. Final Total

  • Original all-in estimate: $38,000

  • Final recorded total: $41,400

  • Variance: +$3,400 (8.9 % over)

The original number included a 12 % contingency. That contingency was fully consumed by the asbestos abatement and the plumber stop-work, then exceeded by the smaller cumulative overruns. The sheet never hid the movement. This post simply freezes it for the record.

Category-by-Category Final Numbers

Asbestos and plumber final invoices with calculator showing combined major overruns

1. Demolition & Disposal — $3,410

  • 20-yard dumpster (two pulls): $835

  • Asbestos testing + full abatement + special disposal: $2,800

  • Protective plastic, zipper walls, tape, scrapers, blades: $210

  • Shop-vac filters and extra demo tools: $65

Original Phase 1 budget had been $2,800. The asbestos tile under the vinyl turned this category into the single largest overrun.

2. Rough-ins (Plumbing, Electrical, Framing) — $8,638

  • Original plumber rough-in: $2,400

  • Week 5 plumber change order (drain, vent, gas upsizing, permit): $1,738

  • Electrician (new circuits, panel work, under-cabinet rough-in): $2,800

  • Framing, blocking, and minor carpentry: $600

  • Temporary kitchen setup materials: $300

  • Miscellaneous fittings, valves, and fasteners: $200

This category absorbed the second major surprise and the cost of doing the wet and gas work correctly instead of cosmetically.

3. Cabinets, Hardware & Installation — $6,977

  • RTA shaker cabinet order: $7,200

  • Partial refund for wrong-hinge doors and missing drawer front: –$287

  • Soft-close hardware upgrades and pulls: $680 (included in original cabinet number above for simplicity; net effect already reflected)

  • Temporary shelving and work-arounds during the delay: $64

Net cabinet cost landed slightly under the original line after the refund. The real cost was time, not dollars.

4. Countertops, Sink & Faucet — $5,225

  • Quartz countertops (templated, fabricated, installed): $4,900

  • Seam adjustment and on-site corrections during install: $325

  • Undermount sink and faucet: $780 (sink/faucet originally budgeted here; final combined)

  • Note: sink and faucet numbers were tracked under finish plumbing in earlier updates but are consolidated here for clarity in the final view.

The countertop category finished over its original locked price because install day refused to stay in the two-hour window.

5. Flooring — $867

  • Rigid-core LVP (220 sq ft including waste and spares): $820

  • Transitions, spacers, moisture meter, knee pads: $47

One of the few categories that stayed comfortably under its original budget and helped offset other overruns.

6. Backsplash, Paint & Finish Surfaces — $1,520

  • Subway tile, thinset, grout, spacers: $1,150

  • Paint, primer, supplies: $370

Installed ourselves. Straight enough. Easy to clean. No drama.

7. Electrical Finish & Lighting — $1,120

  • Recessed lights, dimmer, under-cabinet LED strips, final devices: $840

  • Remaining electrician finish labor: $280

The under-cabinet lighting is the feature we notice every single evening.

8. Appliances — $3,100

  • Range, dishwasher, microwave (mid-range, no unused smart features): $3,100

Purchased early and stored in the garage. No price movement.

9. Tools, Temporary Kitchen & Miscellaneous — $2,543

  • Initial tool haul (five keepers): $349

  • Temporary kitchen propane, paper goods, extra supplies across 10 weeks: $610

  • Dust containment materials: $143

  • Blades, fasteners, caulk, silicone, touch-up, punch-list supplies: $480

  • Final professional clean and detail day: $400

  • Remaining small overruns and sales tax buffer used: $561

This catch-all category is where the daily reality of living through a renovation lives. It is also where the original estimate was most optimistic.

The Contingency Story

We started with roughly $4,500 in contingency (12 % of $38,000).
Asbestos took $2,800.
Plumber change order took $1,738.
Smaller overruns consumed the rest and then some.

By the midpoint we were already writing checks that were no longer “contingency.” They were simply additional cost. The final $3,400 variance is the honest arithmetic of that process.

What the Numbers Do Not Include

  • Our own labor hours (estimated 180–200 hours across both of us)

  • Childcare and meal premium during the heaviest weeks

  • The value of the contractor buddy who answered late-night texts

  • Emotional wear and tear (not billable, fully real)

The $41,400 is cash out the door. The true cost is higher in ways the spreadsheet cannot capture.

Side-by-Side with the Contractor Bids

The three professional bids we received at the start ranged from $62,000 to $81,000 (appliances excluded). Even after our overruns we finished well below the lowest bid. That gap is almost entirely labor and markup. We paid for it with time, dust, and a public spreadsheet that forced us to stay honest about every dollar.

The Sheet Stays Public

The Google Sheet will remain viewable. Categories are frozen. The final total is locked. Future updates will only appear if a warranty item or a latent defect forces new spending. For now the record stands:

$41,400. Demo to dried caulk.

Measure twice, cook once.
And when the last line is entered, leave the sheet public so the next person can see the real arithmetic.

Ready to talk about your own home?

Book a free site visit — our designer will give you advice based on your actual space.

Book a Free Site Visit
Back to Home

Resident Letters

0 letters

No letters yet — be the first to write one.

Leave a Letter